Hartmann-Clark Bros v. State of Illinois

6 Ill. Ct. Cl. 365 Illinois Court of Claims Filed 1929-05-09 No. 1474
Disposition: (No. 1474-Claimant awarded $6,147.29.) Award: $6,147.29 Agency: Department of Public Works and Buildings
Cite as: Hartmann-Clark Bros v. State of Illinois, 6 Ill. Ct. Cl. 365 (1929)
Legacy General 6 awarded 1920s Hartmann-Clark Bros v. State of Illinois 6 Ill. Ct. Cl. 365 1929-05-09 (No. 1474-Claimant awarded $6,147.29.) /opinions/v06-p0386-1/

HARTMANN-CLARK BROS. COMPANY, Claimant, v. STATE OF ILLINOIS, Respondent.

Case summary

Claimant sought $10,000 for losses from an unprecedented flood during bridge construction. The court initially denied the claim, but on rehearing awarded $6,147.29, the amount of expenses approved by the State Highway Department and concurred in by the Attorney General.

Claim type: Contract

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. HARTMANN-CLARK BROS. COMPANY, Claimant, vs. STATE OF ILLINOIS, CONTRACTS-when State not liable for losses sustained by reason of REHEARING-when rehearing will be granted. The Court being fully CONTRACTS-when award will be made. Where the correctness of the OSCAR E. CARLSTROM, Attorney General; FRANK R. EAGLE- 366 HARTMANN-CLARK BROS. v. STATE OF ILLINOIS.

The claimant an Illinois corporation, entered into a contract with the State of Illinois by its Department of Public Works and Buildings for the erection and construction of a girder bridge on a part of the State Bond Issue Route No. 24, Tazewell County, Illinois. It appears by said contract that [*366] claimant was to receive the sum of $23,131.90. The claimant entered upon the performance of his contract and it is alleged that on or about the 27th day of May, 1927, an unprecedented flood occurred which washed away the construction work done on said bridge with materials to be used in the construction of said bridge together with tools belonging to claimant causing claimant a loss for which he asks to recover the sum of Ten Thousand ($10,000.00) Dollars. It further appears after said flood and loss that the Highway Department thought it best to discontinue the contract. The court fails to find that any protest was made by claimant on this ground.

The Attorney General comes and submits the matter to this court for such disposition as the court would care to make.

This court is of the opinion that it would be an unusual precedent to attempt to reimburse a contractor in a loss of this character, it being assumed by the court that a contractor would enter upon a project of this kind mindful of the hazards attendant thereto and while it is unfortunate for claimant to sustain this loss, yet it would appear that a private corporation would not be expected to undertake the problem of underwriting a hazard of this character. The court does not think the State of Illinois ought to be called upon to insure a roadbuilder or bridgebuilder against weather hazards unless the same is specified in the contract.

Therefore it is recommended that the said claim be denied.

On June 26, 1929, upon petition for rehearing, the following order granting rehearing, was filed: The petition for rehearing coming on to be heard, by the Court, and the Court being fully advised in the premises finds that petition for rehearing should be granted and therefore the same is hereby granted.

On January 15, 1930, the following modified opinion was filed: This is a case that has heretofore been passed upon by the court and claim denied and rehearing granted and now the matter comes on for rehearing and the court feels that the expenses incurred, by claimant, the correctness of which was approved by the State Highway Department, and the [*367] defendant, through the Attorney General concurs in the belief that claimant suffered damages in the sum of $6,147.29.

Therefore, the court recommends that claimant be awarded the sum of $6,147.29.

Official volume 6 (Containing cases in which opinions were filed between July 1, 1927–June 30, 1931)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.