Iowa Bridge Company v. State of Illinois

6 Ill. Ct. Cl. 272 Illinois Court of Claims Filed May 9, 1929 No. 1432
Disposition: (No. 1432-Claimant awarded $12,618.51.) Recommended to Legislature: $12,618.51. Not counted in award totals. Agency: Illinois Department of Public Works and Buildings, Division of Highways
Cite as: Iowa Bridge Company v. State of Illinois, 6 Ill. Ct. Cl. 272 (1929)
Legacy General 6 awarded 1920s Iowa Bridge Company v. State of Illinois 6 Ill. Ct. Cl. 272 May 9, 1929 (No. 1432-Claimant awarded $12,618.51.) /opinions/v06-p0293-1/

IOWA BRIDGE COMPANY, Claimant, v. STATE OF ILLINOIS, Respondent.

Case summary

Claimant sought recovery of $12,618.51 in damages for a deficiency incurred while constructing a bridge due to unexpected soil conditions. The court found a misunderstanding regarding soil conditions and recommended an award of $12,618.51, which was granted.

Claim type: Contract

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. CONTRACTS-finding of facts without recommending award. Where the OSCAR E. CARLSTROM, Attorney General; FRANK R. EAGLE-

(Claimants awarded $558.00.)

Official volume 6 (Containing cases in which opinions were filed between July 1, 1927–June 30, 1931)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.