Illinois Court of Claims Opinions
General Court of Claims
Download PDF

Thorlief Larsen & Son v. State of Illinois

43 Ill. Ct. Cl. 33 Illinois Court of Claims Filed 1991-03-18 No. 81-CC-1441
Disposition: (No. 81-CC-1441B-Claim denied.) Agency: Capital Development Board
Cite as: Thorlief Larsen & Son v. State of Illinois, 43 Ill. Ct. Cl. 33 (1991)
General Court of Claims 43 denied 1990s Thorlief Larsen & Son v. State of Illinois 43 Ill. Ct. Cl. 33 1991-03-18 (No. 81-CC-1441B-Claim denied.) /opinions/v43-p0143-1/

THORLIEF LARSEN & SON, INC., Claimant, v . THE STATE OF ILLINOIS, Respondent.

Case summary

The claimant sought $224,060.00 for breach of warranty and contract related to masonry work on a school project. The court denied the claim due to depletion of project funds, despite a joint stipulation that $85,000 would have been paid if funds were available.

Claim type: Contract

Statutes cited: Ill. Rev. Stat., ch. 37, par. 24-5; 74 Ill. Adm. Code 790.60

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. ROLAND W. BURRIS,Attorney General (ERIN M. ~’CONNEL Assistant L, Attorney General, of counsel), for I Respondent.
  2. LAPSED APPROPRlATlONS-mUSOnry contract-joint stipulation approued-insuf ficient funds appropriated-claim denied. The Claimant sought payment from the State for sums due under a masonry contract for work performed at a high school and, although the parties’ joint stipulation as to the amount owed to Claimant was approved, the claim was denied solely because insufficient funds remained for the project, and to render an award would be in effect adding money to the project account, and appropriation of funds is the prerogative of the General Assembly.

ORDER

MONTANA, C.J.

The Claimant, Thorlief Larsen & Son, Inc. (hereinafter referred to as TLS) brought this action, No. 81-CC- I

I

[*34] 1441B, based on allegations of breaches of warranty and breaches of contract against the Respondent’s Capital Development Board (hereinafter referred to as the CDB) seeking compensation totalling $224,060.00 for damages, together with post-judgment interest, costs, and reasonable attorney fees. The case at bar is the second portion of a claim which was bifurcated. The first portion of the claim, No. 81-CC-1441A was previously resolved by entry of judgment in favor of TLS in the amount of $80,872.26 on July 15, 1982. This judgment has been paid.

The case at bar was placed on general continuance in accordance with Ill. Rev. Stat., ch. 37, par. 24-5, and 74 Ill. Adm. Code 790.60 by order of Commissioner Cronin December 14, 1982, pending the disposition of another action arising out of the same circumstances as gave rise to this claim. The collateral action was pending in the circuit court of Cook County.

On February 18,1988, TLS moved to have the case restored to active status and sought leave to file an amended complaint. These motions were granted and the amended complaint was filed. Discovery and several pretrial conferences ensued.

On December 14,1990, a joint stipulation was filed by the parties with the intention of settling this claim. This joint stipulation is now before us for approval.

The stipulation reads in relevant part as follows:

“1. That this claim was brought for work performed by the claimant on the New Jefferson High School project, CDB project No. 762-201-001. That the Claimant was the masonry contractor for the project.

2. That during the course of this contract certain additions and deductions were made to Claimant’scontract balance.

3. That the services for which this claim is made were performed to the specifications and satisfaction of the Capital Development Board.

[*35] I

35 II

I

4. That the project funds and contingency funds for New Jefferson High I School Project, Capital Development Board Project No. 762-201-001 have been

I

depleted. No additional money is available for payment of this claim.

I

5. The respondent agrees that had the State of Illinois, Capital Development Board Project No. 810-072401funds not been depleted the Capital Development Board would have paid claimant Thorlief Larsen & Son, Inc., $85,O00.

WHEREFORE, respondent respectfully moves this Court to enter an order dismissing the claim herein with prejudice.”

I

This Court is not bound by such stipulations but it does not seek to interpose controversy where none appears to exist. The Court does accept and approve the stipula- I tion but is constrained to deny the claim for to do other- 1 wise would be in effect adding money to the project account. Appropriation of funds is the prerogative of the t General Assembly. However, as an advisory body to the I General Assembly and in anticipation of possible further consideration of this matter by the General Assembly, I the Court finds that both TLS and the CDB agree that the services for which this claim is made were per- I1 formed to the specifications and satisfaction of the CDB I

I

and but for lack of funds the CDB would have paid, and TLS would have accepted, the sum of $85,000.00 in satisfaction and settlement of this claim.

It is hereby ordered that this claim be, and hereby is, denied solely because of insufficient funds remaining for the project. ,

t

Official volume 43 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion for: Fiscal Year 1991 – July 1, 1990–June 30, 1991)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.