Lewis University v. State of Illinois

35 Ill. Ct. Cl. 93 Illinois Court of Claims Filed 1982-05-03 No. 76-CC-2606
Disposition: (No. 76-CC-2606-Claimant awarded $2,104.26.) Award: $2,104.26
Cite as: Lewis University v. State of Illinois, 35 Ill. Ct. Cl. 93 (1982)
Lapsed Appropriation 35 awarded 1980s Lewis University v. State of Illinois 35 Ill. Ct. Cl. 93 1982-05-03 (No. 76-CC-2606-Claimant awarded $2,104.26.) /opinions/v35-p0250-1/

LEWIS UNIVERSITY, Claimant, v. THE STATE OF ILLINOIS, Respondent.

Case summary

Lewis University sought reimbursement for a final contract period. The court found that the claimant had exceeded its line item budget by $6,215.45, reducing the disputed amount, and awarded the remaining $2,104.26.

Claim type: Contract

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. TYRONE C. F AHNER, Attorney General (PAUL SENGPIEHL, Assistant Attorney General, of counsel), for Respondent.
  2. APPROPRIATIONS-lapsed appropriation-stipulated settlement. The contract amount which was in dispute was settled on the stipulation of the parties after making a deduction for the amount by which the claim exceeded the line item budget amounts.

This matter coming on to be heard upon a joint stipulation for the final portion of the complaint, which has been agreed to by Claimant, Lewis University, by its attorney, Roman Okrei, and by the Respondent by Tyrone C. Fahner, Attorney General of the State of Illinois, and the Court being fully advised in the premises:

Finds: The stipulation pertains exclusively to the contract period from October 1, 1973, to May 31,1974.

The audit of the program during this contract period from October 1, 1973, to May 31, 1974, showed that Claimant had exceeded its line item contract amount by $6,215.45 and should not receive reimbursement for this amount.

The total contract amount claimed for this final period was $111,858.57 with $93,539.16 already paid, leaving a difference of $8,319.71in dispute. By reducing the $6,215.45 which exceeded the line item budget amounts from the disputed amount, the actual amount remaining for reimbursement on the project for this final contract period was $2,104.26.

[*94] It is hereby ordered that Claimant is granted a final award of $2,104.26 for the contract period from Ociober 1,1973, through May 31, 1974, and that upon the award of this amount, the entire complaint in this matter has been completed.

Official volume 35 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion for: Fiscal Year 1982 – July 1, 1981–June 30, 1982; Fiscal Year 1983 – July 1, 1982 – June 30, 1983)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.