Illinois Court of Claims Opinions
General Court of Claims
Download PDF

Charles F. Bruckner & Sons v. State of Illinois

34 Ill. Ct. Cl. 279 Illinois Court of Claims Filed 1981-06-11 No. 81-CC-1146
Disposition: (No. 81-CC-1146-Claimant awarded $36,383.00.) Award: $36,383.00 Agency: Capital Development Board
Cite as: Charles F. Bruckner & Sons v. State of Illinois, 34 Ill. Ct. Cl. 279 (1981)
General Court of Claims 34 awarded 1980s Charles F. Bruckner & Sons v. State of Illinois 34 Ill. Ct. Cl. 279 1981-06-11 (No. 81-CC-1146-Claimant awarded $36,383.00.) /opinions/v34-p0379-1/

CHARLES F. BRUCKNER & SONS, Claimant, v. THE STATE OF ILLINOIS, Respondent.

Case summary

Claimant sought damages for costs incurred when a project at the Addison Specialized Living Center was unreasonably delayed by the respondent. The court granted the stipulated award based on the parties' agreement.

Claim type: Contract

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. TYRONE C. FAHNER, Attorney General (GLEN P. LARNER, Assistant Attorney General, of counsel), for Respondent.
  2. CONTRACrS-UWard granted based on stipuhtion of parties. An award was granted in accordance with the stipulation of the parties which was approved by the Court of Claims, as there was an agreement as to the fact that the Respondent was responsible for the delay in completing the building project and due to the delay the Claimant incurred greater costs in performing the necessary work.

This case comes before the Court on the joint stipulation of the Claimant, Respondent and the Capital Development Board.

The facts are not in dispute. Claimant performed services for Respondent in the Addison Specialized Living Center during the years of 1978 through 1980. Due to problems which arose between Respondent and its general contractor, the project was considerably delayed. The delay was unreasonable and not attributable [*280] to any act of Claimant, which nevertheless performed its services in accordance with the contract. Respondent concedes that it was responsible for the delay thereof, and that Claimant incurred greater costs in the performance of its work than it would have if the delay had not occurred.

Both parties agree that Claimant suffered damages in the amount of $36,383.00, and that an award in that amount be granted. Claimant, in receiving this award, agrees to waive and relinquish any right to additional damages from Respondent incurred as a result of the delay caused by Respondent.

The Court is not bound to accept without question a settlement such as this, but, at the same time, it does not desire to interpose a controversy where none appears to exist. The joint stipulation submitted herein appears to be fair and reasonable, and we see no reason to question its validity or propriety.

The Court hereby grants an award to Claimant in the amount of $36,383.00 as full and final satisfaction of this claim.

Official volume 34 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion for: Fiscal Year 1981 – July 1, 1980–June 30, 1981)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.