Rosemont Building Supply Co. v. Fillinois

29 Ill. Ct. Cl. 339 Illinois Court of Claims Filed 1974-04-11 No. 74-CC-408
Disposition: (No. 74-CC-408-Claimant awarded $56.45.) Award: $56.45 Agency: Department of Transportation
Cite as: Rosemont Building Supply Co. v. Fillinois, 29 Ill. Ct. Cl. 339 (1974)
Lapsed Appropriation 29 awarded 1970s Rosemont Building Supply Co. v. Fillinois 29 Ill. Ct. Cl. 339 1974-04-11 (No. 74-CC-408-Claimant awarded $56.45.) /opinions/v29-p0358-1/

ROSEMONT BUILDING SUPPLY Co., INC ., Claimant, v. STATE O FILLINOIS, DEPARTMENT O FTRANSPORTATION, Respondent.

Case summary

The claimant sought payment for a contract claim that could not be paid because the appropriation had lapsed. The court awarded the amount due of $56.45.

Claim type: Lapsed Appropriation

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. CONTRACTS-lapsed appropriation. When the appropriation from which a claim should have been paid has lapsed, the Court will enter a n award for the amount due claimant.

The official report prints no opinion text for this claim beyond the heading, headnote, and judge line shown above. The Court's disposition is stated in the heading. See the PDF for the page as printed.

Official volume 29 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion between: July 1, 1973–June 30, 1974)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.