Legacy General 27 awarded 1970s Commonwealth Edison Company v. Illinois Department of Public Aid 27 Ill. Ct. Cl. 197 1971-04-27 (No. 5965-Claimant awarded $128.73.) /opinions/v27-p0211-1/ COMMONWEALTH EDISON COMPANY, A Corporation, Claimant, v. STATE OF ILLINOIS, DEPARTMENT OF PUBLIC AID, Respondent.
Case summary
Claimant sought payment for services rendered under a contract, but the appropriation from which the claim should have been paid had lapsed. The court awarded the amount due.
Claim type: Lapsed Appropriation
AI-generated summary from the opinion text — may contain errors. The opinion
text and PDF above are the official record.
JOSEPH C. SIDLEY, J R . and GEORGE 0. SHAFFNER, Attorneys for Claimant.
WILLIAM J . SCOTT, Attorney General; SAUL R. WEXLER, Assistant Attorney General, for Respondent.
JOSEPH C. SIDLEY, J R . and GEORGE 0. SHAFFNER, Attorneys for Claimant.
WILLIAM J . SCOTT, Attorney General; SAUL R. WEXLER, Assistant Attorney General, for Respondent.
CoNTrucrs-hpsed appropriation. When the appropriation from which a claim should have been paid has lapsed, the Court will enter an award for the amount due claimant.
PERLIN, C.J .
Official volume 27 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion between: July 1, 1969–June 30, 1972)
·
All opinions in this volume
·
Also on CourtListener
This text is OCR/derived from the official volume and may contain errors. The
PDF is authoritative. Boundary pages shared with the adjacent
opinion are reproduced whole, so the page image may show a neighbor's opening or
closing lines; the transcript text itself is opinion-scoped. See
About & sources.