The Carson-Payson Company v. State of Illinois

8 Ill. Ct. Cl. 581 Illinois Court of Claims Filed 1935-05-31 No. 2627
Disposition: (No. 2627-Claimant awarded $3,966.16.) Award: $3,966.16 Agency: Illinois Department of Corrections (State Reformatory for Women at Dwight)
Cite as: The Carson-Payson Company v. State of Illinois, 8 Ill. Ct. Cl. 581 (1935)
Legacy General 8 awarded 1930s The Carson-Payson Company v. State of Illinois 8 Ill. Ct. Cl. 581 1935-05-31 (No. 2627-Claimant awarded $3,966.16.) /opinions/v08-p0571-1/

THE CARSON-PAYSON COMPANY, Claimant, v. STATE OF ILLINOIS, Respondent.

Case summary

Claimant, a contractor, sought damages for delays and increased labor costs caused by the State's rejection of stone work, delayed shipments, and changes in plans during construction of a building at the State Reformatory for Women. The court awarded $3,966.16, finding the delays were caused by the State and the damages justly computed.

Claim type: Contract

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. CONTRACTS-damages caused by act of State-when award may be made for. Where no contention as to law or fact is raised by the State and it clearly appears that claimant fully performed its contract and that it sustained damages, through no fault on its part, but occasioned solely by the acts of the State, in changing plans and specifications, delay in furnishing revised ones and rejection of materials furnished by it, by reason of which claimant was delayed in the performance of its contract, entailing payment of wages while awaiting plans and replacement of materials, and proper State department reports that amount of damages sustained are correctly and justly stated, an award may be made for the amount thereof.

This claim was originally filed March 5, 1933, for redress in the sum of Seven Thousand Three Hundred Fifteen and 82 100 Dollars ($7,315.82) by reason of delay and expense caused to claimant as a contractor, through poor material and delayed shipments by the State. The original claim was dismissed however and the claim in its present form was filed March 6, 1935, for Three Thousand Nine Hundred Sixty-six and 16 100 Dollars ($3,966.16).

Claimant is an Illinois Corporation located at Danville and engaged as contractors in plumbing, heating and ventilation construction work. A contract for this character of work was awarded claimant on December 9, 1931, in the sum of Twenty Three Thousand Twenty-five Dollars ($23,025.00) in connection with the erection of the Medium Security Building at the State Reformatory for Women at Dwight, Illinois.

The general contractor on this project was the Willadson Construction Company. The stone for the building was manufactured and furnished by the State and the latter furnished its own inspectors to inspect the material that was furnished and to see that the plans and specifications were strictly followed. Claimant's damages are alleged to have resulted from delays caused by rejection of a large amount of stone work, some of which was ordered taken down after having been once placed by the masons; also further damage because of delay resulting from changes in the plans amounting to approximately one-fourth of the amount of the original contract, such changes having been made after construction was well under way. Claimant contends that as a result of these delays and intermittent changes, claimant's men were forced to sit idly by causing an increased cost of labor to claimant. Plaintiff also complains that the general contractor failed to keep water pumped out of the basement and that plaintiff was forced to have his own employees remove the water at least ten times in order to be able to continue their work. Claimant was notified on June 4, 1932, that revised architectural plans would be forwarded in the near future and claimant was thereafter compelled to await preparation of these plans from day to day, and to remain in readiness to proceed any time same were delivered; that the authorized changes and enlarged plans were not received by claimant [*583] CHICAGO PRINTERS, INC., A CORPORATION v. 583 STATE OF ILLINOIS.

until September 16, 1932; that due to these delays between May 10th and September 16th a total loss of Three Thousand Nine Hundred Sixty-six and 16/100 Dollars ($3,966.16) represents a conservative total of the damage to claimant. No contention as to law or fact is raised by the State. The record shows that claimant did all of the installation work required of it as quickly as the construction of the building would permit; that during all of the delays claimant was required to maintain a superintendent and a certain force of workmen and foremen and equipment of supplies on the job; that at no time were the delays caused by claimant or its workmen, and that the delays caused claimant unjust losses.

As these delays were largely caused by material changes and alterations in plans, it is legal and just that claimant should be paid therefor. The Architectural Department in a report dated March 21, 1935, states that the claim as now submitted has been thoroughly checked over by that Department and that the damages stated are justly and correctly computed.

An Award is Therefore Allowed in favor of claimant in the sum of Three Thousand Nine Hundred Sixty-six and 16/100 Dollars ($3,966.16).

Official volume 8 (Containing cases in which opinions were filed between July 1, 1933–June 30, 1935, and advisory Opinions furnished University of Illinois)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.