Illinois Court of Claims Opinions
Legacy General
Download PDF

Chicago Heights Coal Company v. State of Illinois

7 Ill. Ct. Cl. 45 Illinois Court of Claims Filed 1931-12-08 No. 1855
Disposition: (No. 1855-Claimant awarded $41,568.89.) Award: $41,568.89 Agency: Division of Highways, Department of Public Works and Buildings
Cite as: Chicago Heights Coal Company v. State of Illinois, 7 Ill. Ct. Cl. 45 (1931)
Legacy General 7 awarded 1930s Chicago Heights Coal Company v. State of Illinois 7 Ill. Ct. Cl. 45 1931-12-08 (No. 1855-Claimant awarded $41,568.89.) /opinions/v07-p0063-1/

CHICAGO HEIGHTS COAL CO., Claimant, v. STATE OF ILLINOIS, Respondent.

Case summary

Claimant sought damages for cancellation of road construction contracts due to invalidity of the Prevailing Wage Law. The court found the claim reasonable and awarded $41,568.99.

Claim type: Contract

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. CONTRACTS-work performed under contract, cancelled before completion because of invalidity of law under which awarded-damages-stipulationwhich award may be made. An award is made herein on authority of Bishop Construction Co. vs. State, No. 1845, ante.

This a suit brought by the claimant, Chicago Heights Coal Co., a corporation of the City of Chicago Heights, County of Cook, State of Illinois, against the defendant, State of Illinois, to recover damages caused by the cancellation of road construction contracts No. 4529 and No. 4586 on State Bond Issue Route No. 52, Section 524 awarded on the 3rd day of September, 1931, and Route No. 53, Section 539-X awarded on the 21st day of September, 1931.

The facts in this case are as follows: that after the complainant commenced performance under the said contracts it received notice from the respondent State of Illinois on the [*46] 6th day of October, 1931, through its Division of Highways, Department of Public Works and Buildings, that no payments could be made for work done under the contracts for the reason that the "Prevailing Wage Law" under which the contracts had been let was held to be invalid and void by the courts of this State and that in the event the claimant proceeded further under the said contracts, it did so at its own peril. When this notice was received the complainant had already completed work under the contract costing $26,582.55, and thereafter complainant's forces and machinery remained idle from October 6th to November 2nd, 1931 thereby necessitating considerable expense in addition to the cost of work completed, for which the claimant asked damages, and the State was then and there so notified.

Thereupon the Division of Highways, Department of Public Works and Buildings, of the State of Illinois, through its Director and Chief Highway Engineer, after making deductions for cement sacks salvaged, reached an agreement in settlement of the damages caused as aforesaid and stipulated to make payment in the sum of $41,568.99. The Attorney General has approved of the said settlement and stipulation; but the Division of Highways could not pay the claim and therefore recommended that a claim be filed with this court.

As there is no dispute as to the facts presented in the claimant's declaration and the evidence establishes the claimant's right of action, the court is of the opinion that the claim is reasonable and should be paid. The court accordingly awards the claimant the sum of $41,568.99.

Official volume 7 (Containing cases in which opinions were filed between July 1, 1931–June 30, 1933)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.